top of page
< Back

Kipling Transit Hub

This project integrates TTC subway, GO regional rail and local and regional bus services (GO, TTC, MiWay) into a single hub through a new inter-regional bus terminal and other supporting infrastructure.

Contractor: EllisDon

Architect: Strasman Architects

Engineer: WSP Canada Inc.

Project Value: $4 M

Steel Weight: 850 Imperial Tons


 

OUR ROLE:

Supply and install of structural steel, metal deck, and a structural steel pedestrian bridge over the train tracks. Steelcon effectively implemented SIN beams into the design to replace large span trusses thus reducing the overall cost of the project and providing savings to the client.


APPROACH:

Steelcon was awarded this project in 2018 and the design consisted of large/long span trusses with intermediate secondary wide flange beams. The project also had a very aggressive schedule.


Part of the challenge for this project was the procurement of the long span trusses, which at the time had an extremely long lead time. EllisDon’s concern was that procurement would significantly delay their schedule. There had also been concerns regarding the overall budget as the design was not yet 100% finalized. In order to assist with this challenge, Steelcon offered our design/assist services and utilization of the SIN beam to replace the long span trusses along with the secondary beams to order to achieve the schedule and maximize cost savings. Another challenge was to replace the trusses while maintaining their overall shape and tapered edges, which served as an architectural feature to the building.


RESULTS:

Steelcon effectively implemented SIN beams into the design to replace large span trusses, resulting in considerable savings passed to the client. Steelcon’s engineers also took full responsibility of the roof structure design as they successfully redesigned 80% of the roof members, which assisted with meeting the overall budget and schedule. Steelcon’s engineers successfully designed the custom tapered trusses, which not only met the design requirements but also served to suit the architect’s overall vision.

Power in Numbers

30

Programs

50

Locations

200

Volunteers

Project Gallery

bottom of page